Location: City Road, March – from Burrowmoor Road to end of City Road.
Start date: 16th February 2026
Duration: 3 weeks
Road closures: Road closed from 20:00-06:00 each night.
How does this affect you?
If you live or work inside the closure, you can ask to pass through. Traffic staff will help you where possible and safe to do so.
We ask that no vehicles are left on the carriageway or footway during the work.
Due to the nature of the work, there will be some noise, however we aim to complete the loudest work early in the shift and as quickly as possible to minimise disruption.
Type of Work: Footway resurfacing, as per the extents highlighted in red below.
Time of Day: The maintenance activities will be carried out between 20:00 and – 06:00 each night and the road will be closed during these hours. We have selected these hours to maximise the safe delivery and efficiency of the workforce and those within the closure.
Additional Information: We expect to be revisiting in March 2026 to resurface the carriageway of City Road. More details will follow closer to the time.